Pacific Boulevard Extension
Planned Improvements:
Phase 1 & 2: Construct a 4-lane section of Pacific Boulevard from Nokes Boulevard to approximately 1 mile north of Nokes Boulevard.

Phase 3:
Construct a 4-lane section of Pacific Boulevard from approximately 1 mile north of Nokes Boulevard to connect to Russell Branch Parkway.

Phase 4:
Construct the remaining 2 lanes of the ultimate 4 lane section of Pacific Boulevard between Nokes Boulevard and Severn Way.


Construction Started:
Phase 2: Spring 2014  |  Phase 3: Fall 2015  |  Phase 4: Fall 2015
Construction Completion:
Phase 2: Spring 2015  |  Phase 3: Fall 2016  |  Phase 4: Spring 2016