Route 625 Interchange (Waxpool & Church Roads)
Planned Improvements:
Construct a partial cloverleaf interchange and a 4-lane bridge carrying Route 625 over Route 28 with a directional flyover ramp from northbound Route 28 to westbound Route 625. Widen existing Route 625 crossing Broad Run from four to six lanes. Construct a bridge on Route 625 crossing over the W&OD Trail.
Construction Started:
Winter 2003
Construction Completed:
Route 625 Interchange, Flyover Bridge and Waxpool Road Widening - Fall 2005.
Church Road Widening and W & OD Trail Bridge - Fall 2006